Progress billing means you invoice a job in stages while the work happens, instead of sending one big bill at the end. You get paid as you go, and the client pays for work they can already see.
If you’ve ever bought $6,000 of materials for a job and then waited six weeks to get paid, you already know why contractors use it.
How progress billing works
You agree on the stages before the job starts. Then each time a stage is done, or at the end of each month, you send an invoice for that part.
A simple flow looks like this:
- The client accepts your quote or estimate.
- You agree on a payment schedule and put it in the contract.
- The client pays a deposit, if you take one.
- You finish a stage and send a progress invoice.
- Repeat until the last stage, then send the final invoice.
Each invoice should show the full contract total, what you billed before, what you are billing now, and what is still left. That way the client never has to guess where the job stands.
Two ways to split the bills
By milestone. You bill a set amount when a stage is done. Demo, rough-in, drywall, finish. This is easy for homeowners to understand because they can walk in and see the stage is done.
By percentage complete. You bill for the share of work done in the period, often monthly. Bigger commercial jobs use this, usually with a schedule of values, which is a list of every part of the job and its price.
For most small contractors, milestones are simpler. Percentage billing makes more sense when a job runs for months.
A sample payment schedule
Here’s a $24,000 kitchen remodel billed by milestone:
| Stage | Share | Amount | Billed total so far |
|---|---|---|---|
| Deposit on signing | 20% | $4,800 | $4,800 |
| Demo and rough-in done | 30% | $7,200 | $12,000 |
| Cabinets and counters in | 30% | $7,200 | $19,200 |
| Final walk-through | 20% | $4,800 | $24,000 |
Check your local rules on deposits. Some states cap how much a home improvement contractor can take up front, so look that up before you set the first number.
How to calculate a progress bill
The math is the same every time:
This bill = (contract total × percent complete) − already billed
Say the contract is $40,000. Last month you billed 25 percent, so $10,000. This month the job is 55 percent done.
- $40,000 × 55% = $22,000 earned so far
- $22,000 − $10,000 already billed = $12,000 this bill
If you signed a change order in between, add it to the contract total first. Otherwise you underbill and the extra work comes out of your pocket.
Where retainage fits in
On some jobs, mostly commercial or bigger residential ones, the client holds back a part of each progress payment. That’s retainage, often 5 to 10 percent. It’s paid at the end, once the work is accepted.
So on that $12,000 bill with 10 percent retainage, the client pays $10,800 now and holds $1,200. Track the held amount on every invoice, because it adds up fast and it’s easy to forget to ask for at the end.
What to put on a progress invoice
Start with a normal contractor invoice template and add:
- The original contract total and any change orders.
- The stage or percentage you’re billing for.
- Previous invoices and payments received.
- This invoice amount, and retainage held if any.
- Remaining balance on the contract.
- Due date and how to pay.
Keep the numbers matching your estimate line items. When the client can check the invoice against the paper they signed, you get paid faster.
Is progress billing worth it?
For anything over a couple of weeks or a few thousand dollars, yes. You keep cash coming in, you don’t finance the client’s job, and if something goes wrong halfway you are not out the full amount.
For a one-day repair, just bill at the end. Progress billing is extra paperwork, so use it where the job is big enough to need it.
Frequently asked questions
What is progress billing?
Progress billing is invoicing a job in parts as the work gets done. Instead of one bill at the end, you send several invoices, each for a stage or a percentage of the total contract.
What is the difference between progress billing and a deposit?
A deposit is paid before work starts. Progress bills are paid during the job, after each stage is done. Many jobs use both: a deposit up front, then progress bills, then a final invoice.
How do you calculate a progress bill?
Multiply the contract total by the percentage of work done in that period, then subtract what you already billed. For a $20,000 job that is 60 percent done with $8,000 billed so far, the next bill is $12,000 minus $8,000, so $4,000.
What is retainage in progress billing?
Retainage is a part of each progress payment, often 5 to 10 percent, that the client holds back until the job is finished and accepted. It is paid with the final invoice.
Is progress billing the same as milestone billing?
Milestone billing is a type of progress billing. You bill when a set milestone is reached, like rough-in or drywall, instead of by percentage complete.